Step 5: Contract Administration and
Site Inspection
During the construction of your project, we offer ongoing
interpretation of the Contract Documents and elaboration
on the detail intended, in order to achieve the best
possible results. If products specified are not available,
we recommend substitutions or adapt the design to fit
a new product.
In remodeling projects, some assumptions must be made
in earlier phases of design about existing conditions
inside walls or below grade and when actual conditions
are revealed during construction, adjustments to the
design are necessary. If a difference of opinion between
Owner and Contractor arises, we attempt to resolve the
disagreement.
We make periodic visits to the construction site to
check on the progress of the work and its conformance
with the Contract Documents. We endeavor to guard you
against defects and deficiencies in the work.
We review the Contractor's applications for payment
and make recommendations to you regarding the amounts
due and payable in accordance with the Contract.
We review and make recommendations regarding the Contractor's
submittals (such as shop drawings, samples, and requests
for substitutions), and prepare Change Orders and other
documentation of decisions made during the construction.
|